AI's power problem: $3.4 billion in gas generators, a nuclear permit, and data centers that may never be built

· 5 min read · Drafted with AI help, reviewed by Kepler Oates

Illustration for: AI's power problem: $3.4 billion in gas generators, a nuclear permit, and data centers that may never be built

Every AI answer runs on electricity, and AI companies are running out of places to plug in. This week brought three signs of how far they'll go to get power: a reported $3.4 billion generator deal by Anthropic, a nuclear permit for a reactor startup backed by Amazon, and a warning that many announced data centers may never be built at all.

As a cloud architect, I'll put it simply: computing capacity used to be limited by chips. Now it's limited by power.

What happened

InteractiveThree power stories from one weekPick a story.
  • Anthropic gas deal: $3.4B for 1.7 GW of generators. Reported by: Financial Times; not confirmed by Anthropic. Seller: OnePWR Solutions (Texas), Caterpillar generators. Why: Generator lead times run years; Anthropic took over existing orders. Where: Not disclosed. Available: Over the next two years.
  • X-energy nuclear: First permit for its small reactors. Approved by: US Nuclear Regulatory Commission. Where: A Dow chemical plant in Texas. Size: Four reactors, 80 MW of electricity each. When: Early 2030s. Backer: Amazon, which committed to buy 5 GW.
  • Phantom data centers: Many may never be built. Who says: Ascend Analytics' Brent Nelson on TechCrunch's Equity podcast. Why: Local opposition, permitting delays and the scramble for power. At stake: Billions in AI infrastructure investment.

Sources: The Neuron, Nov 9; VKTR, Nov 8; TechCrunch, Nov 10; TechCrunch Equity, Nov 11.

Why AI companies are making their own power

  • The grid is slow. Connecting a big new data center can require new transmission lines or new power plants, which take years. Meanwhile, expensive chips sit idle.
  • "Bring your own power." The International Energy Agency calls it a trend: developers generate electricity on site. Anthropic's deal is reportedly the largest known single power-equipment purchase by an AI lab. Elon Musk's xAI has used mobile gas turbines near Memphis, which drew an NAACP lawsuit over air quality.
  • Demand is surging. The IEA estimates data centers used about 485 terawatt-hours in 2025, potentially rising to about 950 by 2030, with AI driving much of the growth.

How big is 1.7 gigawatts?

A gigawatt is a billion watts. To make the reported deal concrete, here's a rough comparison using the US Energy Information Administration's figure that the average US household uses about 10,500 kWh of electricity a year:

StepNumber
Generator capacity1.7 GW = 1,700,000 kW
If it ran every hour of a year (8,760 hours)About 14.9 billion kWh
Average US home per year (EIA)About 10,500 kWh
Homes' worth of electricityAbout 1.4 million

That's an upper bound: generators rarely run flat out all year, and some of this capacity may serve as backup. But it shows why this counts as one of the largest known power purchases by an AI company.

And it's part of a much bigger trend. A Lawrence Berkeley National Laboratory report for the Department of Energy found US data centers used 176 TWh in 2023, about 4.4% of US electricity, and projected 325 to 580 TWh by 2028, or 6.7% to 12%. In other words, data centers could double or triple their share of the grid in five years.

The options compared

Power sourceHow fast it can be addedEmissionsMain catch
Grid connectionOften years (new lines, substations)Depends on local mixLong interconnection queues; upgrade costs can spread to all customers
On-site gas generatorsMonths to two years, if equipment is availableHigh (CO2, local air pollution)Generator backlogs; air permits; local opposition
Small modular nuclearEarly 2030s at the earliest for X-energyVery lowNo SMR operating in the US yet; cost and safety reviews
Solar + batteriesRelatively fast to buildVery lowNeeds lots of land; hard to supply 24/7 alone

There's no perfect option. Gas is what's available now, which is why this deal happened. Nuclear is what many companies want for the 2030s. In between, expect a mix, and expect arguments about who pays.

A worked example: what this means for a typical bill

Electricity prices were already rising before the AI boom fully hit. EIA data show the average residential price rose from 16.0 cents per kWh in 2023 to 16.5 cents in 2024, and EIA estimates about 18.2 cents this year, a nearly 5% increase over 2025.

Here's what that does to a typical household using the 2024 average of 865 kWh a month:

2024 price (16.5¢)2026 estimate (18.2¢)
Monthly bill (energy only)$142.72$157.43
Difference+$14.70 a month, about $176 a year

Data centers are only one reason. Berkeley Lab researchers have said it remains unclear whether broader load growth will raise long-run prices, though spikes in demand can cause significant short-term increases. Grid upgrades, wildfire costs, fuel prices and weather all play a role. In California, wildfire mitigation alone added about 5 cents per kWh to PG&E's charges, according to an EIA analysis reported by EUCI. But where data centers cluster, their effect can be large: EIA data put Virginia, one of the biggest data center hubs in the country, at the steepest year-over-year price jump in February, 26.3%.

That's why the "bring your own power" approach matters to you. When a data center makes its own electricity, it doesn't compete as directly for grid capacity, which can protect local rates, at the cost of more local emissions.

The trade-offs

Gas is fast but dirty. Burning it produces carbon dioxide and air pollution, and methane leaks add to the footprint. The IEA estimates data-center electricity emissions could grow from about 150 million to 350 million tonnes of CO2 by 2035.

Nuclear is clean but slow and unproven at this size. No small modular reactor is operating in the US yet. The Union of Concerned Scientists criticized X-energy's permit, saying critical safety questions were pushed "to a later date."

And many projects may evaporate. Some announced data centers will never get built, which matters if your town is weighing one. The headlines can overstate what's actually coming.

Anthropic's own promise. In February, Anthropic pledged to bring new power generation online to match its data centers' needs and to cover consumer electricity price increases tied to its facilities, VKTR reports. This deal will be one of the first tests of that pledge.

What it means for you

  • Your electric bill. When data centers draw from the grid, utilities may need new infrastructure, and those costs can show up in everyone's rates. On-site generation can relieve that, but competition for gas supply can push local prices up. Watch your utility's rate-increase requests; they're public, and you can comment.
  • If a data center is proposed near you, ask three questions at the public hearing: Where will its power come from? Who pays for grid upgrades? What are the air and water impacts? Our look at Santa Clara's data centers shows the local tax side.
  • Lower your own bill. Check whether your utility offers a time-of-use plan and shift laundry, dishwashing and EV charging to off-peak hours. Smart plugs on idle electronics and a programmable thermostat help too. Then put your real monthly electricity cost into the free budget planner below so price increases don't surprise you.
  • Keep perspective. AI isn't going to stop for lack of power, but where that power comes from is now a local decision as much as a tech one.